TESTING & COMMISSIONING

Transformer Testing and Commissioning, Relay Testing and Substation Pre-Commissioning

Tachyons Energy Private Limited provides transformer testing and commissioning, protection relay testing and substation pre-commissioning for installations from 11kV to 440kV. The work includes insulation resistance, winding resistance, ratio and vector group tests, tan delta and capacitance, oil filtration with BDV testing, primary and secondary injection, and circuit breaker timing, all recorded in reports that support inspectorate approval and energisation. The company serves utilities, industries and generation plants from Kerala, India.

  • Transformers
  • Relays
  • CTs / PTs
  • Circuit breakers
  • Earthing

Transformer tests before energisation

A power or distribution transformer is tested at site after erection to confirm that it has not been damaged in transport and that it matches its factory test results. Site results also become the baseline for condition monitoring over the transformer’s life.

  • Insulation resistance and polarisation index (PI) of windings
  • Winding resistance on every tap, which also checks tap-changer contacts
  • Turns ratio on each tap and vector group verification; typical acceptance is within ±0.5% of nameplate
  • Tan delta (dissipation factor) and capacitance of windings and bushings
  • Magnetising current and magnetic balance checks
  • Protection and alarm checks of Buchholz, oil and winding temperature indicators, PRV and OLTC

Oil filtration and BDV testing

Transformer oil must be dry and gas-free before the unit is charged. Vacuum oil filtration heats the oil and passes it through a vacuum chamber to remove moisture and dissolved gas, and the breakdown voltage (BDV) test confirms its dielectric strength. A typical acceptance value for EHV-class equipment is BDV of 60 kV or more across a 2.5 mm gap, per the applicable IS / IEC limits.

  • Vacuum oil filling of new transformers and reactors
  • Multi-pass oil filtration with a temperature and vacuum log
  • BDV testing of oil samples before and after filtration
  • Oil sampling for laboratory analysis where specified

Relay testing: primary and secondary injection

Secondary injection applies test currents and voltages directly to a protection relay to verify pickup, characteristic and timing against the approved settings. Primary injection passes current through the primary side of the CTs to prove ratio, polarity and the complete circuit from CT to relay, and the stability of differential schemes. Together they show that protection will operate for a fault and stay stable when there is none.

  • Secondary injection of numerical and electromechanical relays
  • Primary injection of CT circuits, busbar and transformer differential schemes
  • Relay coordination study review and settings loading
  • Trip testing through lockout relays to the circuit breaker
  • As-left settings files and relay test reports

Substation pre-commissioning

Pre-commissioning covers every item of the substation, not only the transformer. Each test is recorded against the equipment and bay so that the installation can be submitted to the State Electrical Inspectorate and charged under a controlled switching programme.

  • Circuit breaker timing, pole discrepancy and contact resistance
  • CT and PT ratio, polarity, magnetisation and burden checks
  • Isolator alignment and interlock checks
  • Insulation resistance of switchgear and cables
  • Earth-mat and equipment earth resistance by the fall-of-potential method
  • Scheme, alarm and SCADA point-to-point checks

HOW THE WORK RUNS

How we deliver testing & commissioning

  1. 01

    Document and settings review

    Collection of factory test reports, OEM manuals, schematics and the approved relay settings so that site results can be compared against them.

  2. 02

    Test plan and equipment mobilisation

    A test schedule by bay and equipment, and mobilisation of calibrated test kits for injection, insulation, ratio, tan delta, timing and oil testing.

  3. 03

    Equipment-level testing

    Transformer, breaker, instrument transformer, cable and earthing tests, with oil filtration and BDV testing where oil-filled equipment is involved.

  4. 04

    Protection and scheme testing

    Secondary and primary injection, trip and interlock checks, and alarm and SCADA verification across each bay.

  5. 05

    Reports and inspectorate submission

    Signed test reports indexed by bay, punch list closure and documentation support for the State Electrical Inspectorate.

  6. 06

    Energisation and on-load checks

    Charging under the switching programme, soak period, and on-load checks of differential stability, metering and SCADA values.

QUESTIONS & ANSWERS

Testing & Commissioning: common questions

Straight answers to what clients ask us most before a project starts.

What tests are done on a transformer before commissioning?

Typical site tests include insulation resistance and polarisation index, winding resistance, turns ratio on every tap, vector group, tan delta and capacitance, magnetising current, and oil BDV. Protective devices such as the Buchholz relay, temperature indicators and pressure relief valve are also checked. Results are compared with the factory test report before the transformer is charged.

What is a BDV test?

BDV (breakdown voltage) testing measures the voltage at which a sample of insulating oil breaks down between two electrodes set at a standard gap, commonly 2.5 mm. It indicates how much moisture and contamination is in the oil. Low BDV values mean the oil needs filtration before the transformer is energised.

What does a tan delta test show?

A tan delta test measures the dissipation factor of insulation, which rises when insulation contains moisture, is contaminated or has aged. It is carried out on transformer windings, bushings, CTs and CVTs. At commissioning it confirms the insulation is in good condition and gives a baseline for comparing future test results.

What is the difference between primary and secondary injection testing?

Secondary injection applies test signals directly to a relay’s input terminals to check its settings, operating characteristic and timing. Primary injection drives current through the primary side of the current transformers, so it proves the CT ratio, polarity and wiring all the way to the relay. Secondary injection tests the relay; primary injection tests the whole measuring circuit.

Why is transformer oil filtration needed?

New transformer oil absorbs moisture and air during transport, storage and filling, which lowers its dielectric strength and can damage the insulation. Vacuum filtration heats and degasses the oil and removes water until BDV and moisture values meet the specified limits. It is also used during maintenance when oil test results deteriorate.

Can Tachyons Energy test equipment installed by another contractor?

Yes. Tachyons Energy carries out testing and pre-commissioning as part of its own substation and panel scope, and as a separate testing service on installations erected by others. The available drawings, factory test reports and relay settings are reviewed first so that site results can be checked against them.